November 01, 2019
By Tom Perkins, Owner’s Representative
[…]
On the inside, drywall framing of the rooms is nearly complete on all floors, followed closely behind by the electrical, HVAC and plumbing trades. Both town inspectors and third party consultants have been involved with the quality control review of the work put in place by the nearly 100 men and women working each day at the site. Painting of interior walls is scheduled to start in mid-November.
[…]